Al-Arab Contracting Company Building
Al-Arab Contracting Company Building
الرياض
Company
الضويان معماريون
التصميم التجاري
Sustainability Assessment Project Code
CML-DC-26-103
Project Stage
التصمیم والانشاء
Documents / Certificates

Design Approval Document
It is a document issued once the requirements of the Sustainability Assessment Service for the design phase have been met.
Document Issuance Date
20-05-2026
Sustainability Assessment Service Criteria
Achieved Points:
26
Site Sustainability
6/4
SS-01
Sewage, Flood and Rainwater Management
1/1
SS-02
Ecological Assessment and Protection
1/1
SS-03
Construction Environmental Management
2/2
SS-07
Previously Developed Land
2/0
Materials and Waste
7/6
MW-02
Construction Waste Management
2/2
MW-04
Non-Polluting Insulation Materials
1/1
MW-05
Sustainable Materials
3/3
MW-06
Life Cycle Assessment
1/0